Acadian-Haynesville Pipeline Offsite Mitigation Project, Project Manager

Ms. Fetterman provided project management, WVA functional assessment analysis and senior technical oversight services for the permitting of this 170-acre permittee-responsible offsite bottomland hardwood mitigation project compensating for bottomland hardwood and cypress-tupelo wetland losses associated with the construction of an interstate pipeline.  This 277 acre site, also located in Rapides Parish and directly adjacent to the Central Louisiana Mitigation Bank Project, was an extremely time-sensitive project requiring a 2 week turnaround.  Ms. Fetterman effectively coordinated senior ecological and engineering staff from her previous firm to produce a complete mitigation work plan to the client to enable them to submit their permit application prior to changes in New Orleans District functional assessment policy and complete timely public noticing of the project.